CANNONSBURG — Two months from now Cannonsburg water should be flowing to homes in the Argillite area of Greenup County, thanks to a pipeline project that has passed the final hurdles.
The Cannonsburg Water District has hired contractors to install 5.5 miles of pipe along the Industrial Parkway between the current terminus at Sand Gap to Ky. 207, where it will connect with the Greenup system, Danny Clarkston, general manager, said.
The influx of water from the Cannonsburg system will alleviate pressure and quality problems that for years have plagued the Argillite area, where residents are accustomed to almost weekly advisories to boil their water.
The project will cost about $273,000, most of it funded by state money through the Kentucky Infrastructure Authority, said project engineer Paul Amburgey.
The contractor has 60 days to complete the project once the materials arrive, Amburgey said. That means the water should be flowing by August.
Cannonsburg will sell the water to Greenup, which will then bill customers, said Greenup Mayor Donna Hewlett. The connection will serve about 350 homes. Greenup, which owns and operates the system that covers much of the county, will be able to add 325 more customers in its next expansion.
“This is perfect timing with phase 8,” Hewlett said.
The city recently received state approval of a study that analyzed the system to locate problems. Completing the study was a condition for approval of the expansion, which will serve the Schultz area.
The expansion is expected to start in about a year.
Buying the water from Cannonsburg won’t cost any more than making it in the city’s water plant, Hewlett said.
The Cannonsburg connection also will provide backup water supplies, should the system ever fail.
MIKE JAMES can be reached at mjames@dailyindependent.com or at (606) 326-2652.
Local News
Water on the way to Greenup
Project to cost $237,000
- Local News
-
-
Firefighters, city reach settlement on overtime
The city of Ashland has reached an agreement with firefighters involved in a dispute involving overtime wages after an audit by the Kentucky Labor Cabinet.
-
Plea in Greenup love triangle
A Greenup County man on Friday admitted in court that in August 2010 he shot to death a Washington man who’d traveled across the country to be with his former girlfriend.
-
Putnam restoration gets additional $50K
The Putnam Stadium Restoration Foundation got a $50,000 boost from The Woodlands Foundation.
-
Kentucky schools get waiver on No Child Left Behind
Kentucky and nine other states received waivers Thursday from the federal No Child Left Behind Act, in exchange for putting their own improved accountability systems in place.
-
Sweet harmony
Many women all over the world travel miles every week, just to sing with a barbershop chorus.
-
Bankruptcy filings: 2/10/12
Bankruptcy filings in the Eastern District of U.S. Bankruptcy Court include the following:
-
Russell Independent School District
A new gym floor at Russell High School will cost somewhere between $71,000 and $107,000, school board members learned Thursday.
-
Workers reject contract offer
Hourly workers at Marathon Petroleum’s Catlettsburg refinery on Wednesday rejected a contract offer from the company.
-
UW campaign tops $780,000
While the economy of this region continues to struggle, the people of northeastern Kentucky again proved this is a caring and giving area by easily surpassing the ambitious $750,000 for the 2011 campaign of the United Way of Northeast Kentucky.
-
LRC plans to appeal judge’s ruling
The leadership of the General Assembly announced Thursday it plans to appeal Franklin Circuit Judge Phillip Shepherd’s ruling that the legislature’s plan to re-draw state legislative boundaries is unconstitutional.
- More Local News Headlines
-
Firefighters, city reach settlement on overtime